Exemption Levels for Soil, Sludge and Scale in Qatar
October 14, 2026
9 min read
DITEC Experts, Radiation Protection Team, ALDuha Institute for Training and Environmental Consulting

Three rows, three streams, three sets of isotopes
A separator vessel is opened and a pile of solids comes out. A yard has soil under an old tank. A pipe has a hard crust on its inner wall. These are three different streams in Annex 1, and each row names its own isotopes and its own figure. A single number does not cross from one row to another.
Two words first. An isotope is one form of an element, and the rows name them by symbol and number, such as radium 226. A becquerel per gram is a concentration: decays per second in each gram of the material, which is how a laboratory reports a solid sample.
The gate for all three rows is the same gate: article 5. Below the levels of Annex 1 the exemption applies, and it is an exemption from applying the regulations in force. Above them the wording of the article is that the material is treated as radioactive contaminants, and collecting, transporting, storing and disposing of it are required under these rules.
The three rows, transcribed
Soil and sludge: exemption levels for soil contaminated with sludge of naturally occurring radioactive material with the isotope radium 226 or radium 228, lower than 0.185 picocurie per gram for soil of 15 cm depth, or 5.55 becquerel per gram for soil deeper than 15 cm, over an area of 100 square metres above the natural background level; or a portable instrument reading of 0.25 microsievert per hour above the natural background level.
Hard scale in oil equipment: the radioactive activity of the radioactive isotopes radium 226 or radium 228 not exceeding 1.1 becquerel per gram in oil equipment.
Hard scale in gas equipment: the radioactive activity of the radioactive isotopes lead 210 or polonium 210 not exceeding 0.2 becquerel per gram in gas equipment. The oil row and the gas row name different isotopes and different figures, and the gas figure is the smallest number in the whole annex.
The three rows side by side
| The stream | The isotopes the row names | The figure, as transcribed |
|---|---|---|
| Contaminated soil with sludge | Ra 226 or Ra 228 | Two units in one sentence: 0.185 picocurie per gram for 15 cm depth, or 5.55 becquerel per gram for more than 15 cm, over 100 square metres, above the natural background; or a portable instrument reading of 0.25 microsievert per hour above the natural background |
| Hard scale in oil equipment | Ra 226 or Ra 228 | 1.1 becquerel per gram |
| Hard scale in gas equipment | Pb 210 or Po 210 | 0.2 becquerel per gram |
The soil row carries two units, and we do not reconcile them
This is the most important line on the page. The soil and sludge row names two units inside one sentence: picocurie per gram for the shallower depth, and becquerel per gram for the deeper one. The two are different units of the same kind of quantity, and by our own arithmetic 0.185 picocurie per gram is close to 6.85 becquerel per gram, which is not 5.55.
What we do with that is exactly three things. We transcribe the row as it stands. We record the difference and attribute the arithmetic to ourselves. And we put it to the Ministry as a question. What we do not do is convert one figure into the other, or assume the text means one unit and wrote another, or quietly correct it. A published figure is not ours to amend, and a facility that builds a file on a converted number has built it on our arithmetic rather than on the text.
The row has two further features that are easy to miss. The figures are tied to a depth, 15 cm and more than 15 cm, and to an area of 100 square metres. And it offers a second route that is not a laboratory route at all: a portable instrument reading of 0.25 microsievert per hour above the natural background level. Note the words above the background here, which are not the words of the equipment row, where the background is included in the figure.
Why a sludge pile is the hardest of the three
Scale is a deposit on a surface and it is reasonably uniform where it forms. Soil is layered, and the row answers that with a depth and an area. Sludge is a mixture by its nature: solids, heavy hydrocarbons, sand and corrosion products in one pile. So one sample from one drum describes that drum and not the pile.
The practical consequence is in the paperwork rather than in the figure. Keep the sample record and the stream record as two separate things, write how many samples were taken and from where, and never let a single result stand as the description of a heap. And because the soil row speaks of soil contaminated with sludge, the name on the record matters: a pile called soil and a pile called sludge are not read against the same line of the annex in the same way.
What to do with a pile in front of you
The order below is reading and record keeping. It is not a laboratory method and it does not produce a result.
A worked case, and why it stops at a question
A pile is taken out of a separator vessel on an oil facility. A laboratory reports 1.0 becquerel per gram for radium 226 on one sample.
The tempting reading is to compare 1.0 with the 1.1 named for hard scale in oil equipment and call it below the level. That comparison is wrong, because the material is sludge out of a vessel and not hard scale on a pipe wall, and the annex gives them different rows.
The row that does cover it is the soil and sludge row, and that row is the one with two units in one sentence, tied to a depth and an area that a pile in a drum does not obviously have. So the honest stopping point is a question and not a verdict: which unit governs, and how the depth and area apply to material that has been removed from equipment.
And one sample is one sample. The pile is a mixture, so the number of samples and where they were taken from go in the record next to the result.
Four steps before any comparison
Name the stream in the words the annex uses, and write that name on the record rather than a local nickname.
Match the stream to its own row, and do not borrow a figure from a neighbouring row because the number is close.
Record how many samples, from where, by which laboratory and on what date, and keep the sample record separate from the stream record.
Put the unit question in the soil row to the Ministry in writing, quoting the row in full, and do not convert between the units yourself.
Frequently asked questions
Which unit governs the soil row, picocurie or becquerel?
The row names both, each tied to a depth, and we transcribe it as it stands. By our own arithmetic the two figures are not equivalent. We do not choose between them and we do not convert, and this is one of the three questions we put to the Ministry out of this batch.
Can I use the oil scale figure for a gas facility?
No. The annex gives the two their own rows with their own isotopes: radium isotopes for oil equipment and lead 210 or polonium 210 for gas equipment, with different figures. The rows are not interchangeable.
Does a portable instrument reading replace a laboratory result?
The soil row names a portable instrument reading of 0.25 microsievert per hour above the natural background level as part of what it says, and reading it as a separate route is our reading, attributed to us. Whether the Ministry accepts it in place of a laboratory result for a given case is for the Ministry, and we do not answer that for it.
Is a pile below the level simply exempt?
Article 5 exempts from applying the regulations in force, and it attaches a condition of application: that the waste is arising from practices subject to licensing and registration. We quote the exemption with its condition and we do not widen it.
Who takes the sample and who measures it?
A specialist, and a laboratory. The Institute works in training and consulting and does not run laboratory analysis, so the answer to a concentration question comes from a laboratory report with its date and method, not from this page.
Technical note
Watch the reference level in each row. The equipment row says the background is included in its dose figure. The soil row says above the natural background level. Those are opposite instructions about the same background, and using one row habit on the other row changes the answer.
And a mixture is not described by one number. Sludge is solids, hydrocarbons, sand and corrosion products together, so the sampling plan is part of the result and belongs in the record beside it.
One more thing on measurement, because every figure on this page is a measured figure. The reading is taken by someone qualified to take it, with an instrument whose calibration is current and whose response was checked before the work, and the instrument has to respond to the radiation actually present and at the energies present. A gamma probe does not reliably detect an alpha emitter. And a result is written down with its date, its instrument and its method, because a reading without those three is not evidence a year later.
Where DITEC stands, and what this text is
ALDuha Institute for Training and Environmental Consulting (DITEC) works in training and consulting only. Naming a stream against the annex, and building the records that a sample result sits in, is training and consulting work. Producing the result is laboratory work. The Institute does not run a laboratory analysis service, does not calibrate instruments and does not test equipment, and field surveys are carried out through specialist partners. Licensed training is what the Institute offers, and nothing in a training programme or in this explanation is an undertaking that a licence will be issued or that it will be issued within any period.
A note on the authority: the text names the Ministry of Environment. Today that competence sits with the Ministry of Environment and Climate Change, Radiation Protection Department. The unit question in the soil row is one we put to that department. The successor reading is ours, not the wording of the decision, and where the decision is quoted, the original wording is kept in the Arabic text of this article.
This article is an introductory explanation of a published regulatory text and is not a legal opinion.
Quick Actions
Radiation protection programmes for NORM in oil and gasRequest a radiation protection consultationIn this article
Related Blog
Explore more articles in NORM & Oil & Gas

October 14, 2026
Produced Water Discharge Limits Under Qatar NORM Rules
The produced water row of Annex 1 allows direct discharge on two conditions together: a concentration at the discharge point, and a four week total.
Read more
October 14, 2026
When Equipment Counts as Contaminated Under Qatar NORM Rules
Article 6 of Decision 45 of 2013 sets one detection threshold: twice the radiation background in the State. That background value is not in the decision.
Read more
October 14, 2026
When Contaminated Equipment Is Exempt Under Qatar NORM Rules
Article 5 of Decision 45 of 2013 exempts waste below the Annex 1 levels. The equipment row gives two surface figures and one dose figure.
Read more